Wednesday, April 7, 2010

Merz Renovation Update Status




Project Manager: Greg Cook
Superintendent: Jim Green
Below is the work status of Merz:

Phase One

Interior store front glazing nearing completion
Final Painting in progress
Ceiling tile install nearing completion
Flooring install in progress
Installing toilet fixtures
Fabricating casework
Coordinating Board Room Table / Credenza fabrication
IT Area structural modifications nearing completion
IT Area wall framing in progress
Coordinating IT switch-over
Fire protection trim out in progress
Fire alarm system upgrades in progress
HVAC trim out in progress
Electrical trim out in progress

Phase Three

Wall framing complete
Wall rough-ins complete- awaiting inspections

Existing Office Area

Coordinating AV / Data improvements at existing conference rooms

Exterior

Coordinating Patio / Landscape design