January 24, 2013 - HICAPS
is currently executing two task order projects within our VA VISN 11 MATOC with
our teaming partner Shiel Sexton. One of the projects entitled “Upgrade Cooling
Tower Efficiency” consists of removing and replacing a cooling tower at the
Roudebush VA Medical Center in Indianapolis, IN. The project value is $2.4M and
is slated to complete mid-March 2013. This facility has a total of two
towers with a total of 5 cells. This project entails removing one of the towers
having two cells and replacing with a new efficient tower. The three cell tower
is to remain and was left in operation until late Dec. 2012 when temperatures
consistently remained below 50 degrees. Along with demolition of the two cell
tower and associated concrete basin, an existing screen wall with foundations
was demolished and will be replaced at the end of the project. Once demolition
of the tower and basin was complete, excavation began to allow for the new
concrete basin and lid. The concrete basin and lid have been poured with
structural steel installation to support the tower mounted on the lid occurring
during the end of Jan. 2013. The extreme cold temperatures in Indianapolis
during concrete pours added an extra challenge to ensure consistent cure times
and temperatures and the avoidance of thermal shock. The cooling tower delivery
and erection is scheduled to begin Jan. 28 and will have a 2 week duration.
During erection of the new cooling tower, the existing tower will be connected
to the new CW piping and pumps. It is scheduled to be back in operation early
Feb. 2013. Once the erection of the new tower is complete it will be connected
to the CW piping/pumps and will be well on the way to commissioning and
turnover to the VA.
No comments:
Post a Comment