Route 58 Bypass





Another success for HICAPS & BHI. Schedules were produced by David Steger of BHI with HICAPS' assistance and project reviews and audits over the last 3 ½ years.

As we enter our 4th (and final) season of the $83 million Rte 58 Bypass BHI is poised to complete the project almost two months early. Since the notice to proceed over 2 million cubic yards of cut/fill have been handled and 8 bridges constructed. Careful planning and monitoring of the plan over the 4 years of project has allowed BHI to achieve all of its construction season goals (8months of intense production and 4 months of winter slow down per year). Season goals are set from March – Nov each year.

NTP was given 10/02/07. Projected substantial completion of the 5.3 mile Bypass is 09/01/11.